TM 3-1040-214-12
(8) Disconnect the quick-disconnect coupling
(10) Check the pressure reading on the
half (3, Fig. 4-5) from the pipe and cap assembly.
pressure gage. It should stabilize between 30 and 50
psi. The pressure regulator setting is 40 10 psi.
(9) Install the pressure gage between the
hose assembly and pipe and cap assembly.
(11) If pressure gage reading is less than 30
psi, repeat operations (7) to (10) above.
c. Adjusting Procedure.
(12) If pressure gage reading is above 50 psi,
(1) Perform the operation in b above.
close the pressure tank valve. Open the shutoff valve to
(2) Fingertighten
needle
valve
(1) and
vent pressurized air. Repeat operations (3) to (10)
needle valve (2) (Fig. 4-5).
above.
(13) Close the pres sure tank valve.
NOTE
(14) Open
the
shutoff
valve
to
vent
the
If there is a needle valve on the side
pressurized air.
of the pressure regulator, check to
(15) Check and test adjustment of pressure
see that the needle valve is tight.
regulator (d below).
NOTE
d. Testing Pressure Regulator After Adjusting.
Needle valve 1 and 2 should not be
(1) Close the shutoff valve.
removed; they are not interchangeable.
(2) Slowly open the pressure tank val ve and
(3) Loosen needle valve 1 slowly; four
check the pressure gage. If the gage indicates a
complete turns to allow pressurized air to escape from
pressure between 30 and 50 psi, the adjustment is
the dome.
correct.
NOTE
Discharge of air is indicated by a
NOTE
hissing sound.
If the pressure gage indicates a
pressure below 30 psi or above 50
psi, refer to c above.
(4) After hissing noise ceases, close needle
valve 1.
(3) Test fire the disperser. During test fring,
i
(5) Open the pressure tank valve slowly. If
the pressure gage reading is acceptable up to 90 psi. If
the gage indicates a rise in pressure, close the pressure
the gage reading exceeds 90 psi, perform the following:
tank valve immediately. A rise in pressure indicates that
the pressure regulator is defective.
(a) Close the pressure tank valve.
(6) If the pressure regulator is defecti ve,
(b) Open the shutoff valve.
perform the following operations:
(a) Close the pressure tank valve.
(c) Replace
the
pressure
regulator
(b) Open the shutoff valve to relieve air
pressure in the agent section.
(d) Adjust
the
pressure
regulator
(c) Replace the pressure regulator
(c above).
4-37. Delivery Pipe Coupling
(7) If pressure gage indicates no rise in
Organizational maintenance personnel are authorized to
pressure, open needle valve 2 slowly about one half
replace the delivery pipe coupling.
turn. Air will escape at the needle valve.
(8) Open needle 1 very slowly until pressure
a. Removal.
gage indicates a pressure reading. Immediately close
(1) Purge the air in the pressure system
needle valve 1.
(para 4-10a).
(9) Close needle valve 2.
(2) Remove coupling (12, Fig. 4-6) from the
delivery pipe (13).
NOTE
b. Assembly.
The pressure reading on the pressure
gage will slowly increase until the
(1) Apply anti-seize compound or tape on the
pressure in the agent tanks is
delivery pipe threads (12).
stabilized.
(2) Screw the coupling (12) on the delivery
pipe threads and tighten.
4-25
|