TM 3-1040-214-12
a. Removal.
b. Assembly.
(1) Purge the air in the air pressure system
(1) Screw the handle (2-1) into the body of
the shutoff valve (22) and tighten setscrew (23).
(2) Remove the safety head (12) and washer.
(2) Screw the shutoff valve (22) into the
adapter (9). Tighten the shutoff valve (22) in the adapter
b. Installation
(9) as shown in figure 4-5.
(1) Check to see that a washer is located on
(3) Attach the vent tube (21) to the shutoff
the threaded portion of the safety head (12).
valve (22) and tighten the nut.
(2) Connect the safety head
(12) to the
(4) Connect each hose assembly (2) to the
safety valve (11) and tighten.
safety valve adapter (9) and tighten.
4-34. Preformed Packing and Setscrews
(5) Connect the diffusion tube nut (8) to the
safety valve adapter (9).
Organizational maintenance personnel are authorized to
replace the safety valve adapter preformed packing and
(6) Cross the open ends of both hose
screw.
assemblies (2) and connect the quick-disconnect coupling
halves (3) to opposite pipe and cap assemblies (4).
a. Removal
(7) Lace the carrier pack (8, Fig. 4-10) to the
(1) Purge the air in the pressure system (para
frame (10).
4-10a).
4-36. Adjusting Pressure Regulator
(2) Remove the pressure tank and valve
assembly (para 4-10b).
a. General. Organizational maintenance personnel
are authorized to adjust the pressure regulator.
(3) Remove the screw (7, Fig.
4-5) and
Adjustment is performed upon receipt of an M3
preformed packing from the safety valve adapter (9).
disperser, monthly, and when a pressure regulator has
b. Installation
been replaced.
(1) Install preformed packing (6) and screw
b. Preparation for Adjusting.
(7).
(1) Unlace the canvas pack carrier on one
(2) Install the
pressure
tank
and
valve
side to expose the pressure regulator.
assembly (para 4-10c).
(2) Close the pressure tank valve by turning
4-35. Shutoff Valve, Handle, and Vent Tube
the valve handle clockwise (Fig. 4-9).
Organizational maintenance personnel are authorized to
(3) Open the shutoff valve by turning the
replace the shutoff valve, handle, and vent tube.
shutoff valve handle (24, Fig. 4-5) counterclockwise.
a. Removal.
(4) Close the shutoff valve by turning the
handle (24) clockwise.
(1) Purge the air in the pressure system
(para 4-10a).
(5) Check pressure in pressure tank (para 4-9).
The pressure for testing purposes should be a minimum
(2) Unlace one side of the carrier pack.
of 2,000 psi.
(3) Disconnect the quick-disconnect couplin g
half (3, Fig. 4-5) on each hose assembly (2) from the
NOTE
pipe and cap assembly (4).
Use
T1
talc
when
checking
(4) Disconnect the diffusion tube nut (8) from
adjustment of a replaced pressure
the safety valve adapter (9) and remove the pressure
regulator and also when performing
regulator and attaching parts.
required monthly adjustment of
pressure regulator.
(5) Remove hose assemblies (2) from the
adapter (9).
(6) Remove vent tube (21).
(6) Fill the agent tanks with T1 talc.
(7) Loosen set screw (23) and unscrew
(7) Obtain a pressure gage from the M27 riot
handle (24) from the shutoff valve (22).
control service kit (TM 3-1040-221-12).
4-24
|