TM 11-5995-208-24&P-1
INSULATION BREAKDOWN/LEAKAGE TEST (CONT)
GENERAL
WARNING
Do not turn Insulation Breakdown Test Set AN/GSM-6 on after setting it up. Serious
injury could result to personnel due to electrical shock.
1. Set up Insulation Breakdown Test Set AN/GSM-6 as shown above.
2. Do complete Preoperational Procedures on AN/GSM-6 as outlined in
TM 11-6825-273-12.
3. Do a complete Stopping Procedure as outlined in TM 11-6625-273-12.