TM 5-3610-254-14
Table 5-1. DIRECT SUPPORT TROUBLESHOOTING (cont)
MALFUNCTION
TEST OR INSPECTION
CORRECTIVE ACTION
b.
Disconnect the electrical cable which extends between the control box and the air
conditioner at the air conditioner connector.
c.
Remove the cable clamps which secure the control box cable to the shelter wall.
d.
Remove the screws and lockwashers which attach the control box to the shelter wall and
remove the box complete with cable.
CAUTION
Extreme care must be exercised while performing maintenance on humidistats and/or thermostats.
They are designed to operate within a very small change in temperature and will easily become
maladjusted.
e.
Check the function switch to ensure correct control operation and smooth rotation to
each switch position.
Step 2.
Test for defective heating elements. Replace defective elements as necessary.
2.
BLACKOUT WARNING BUZZER WILL NOT ACTIVATE WHEN SWITCH IS DEPRESSED
Step 1.
Inspect main power service box for correct positioning of BLACKOUT BUZZER circuit breaker.
Position BLACKOUT BUZZER circuit breaker to ON.
Step 2.
Inspect for correct electrical connection at buzzer as follows:
a.
Position BLACKOUT BUZZER circuit breaker in main power service box to ON.
b.
Remove the screws that attach the buzzer cover to the base and remove the cover.
c.
Using a suitable meter or test light, check for continuity at wire connections when blackout
warning switch is depressed.
Repair or replace defective buzzer as described in paragraph 5-22..