SB 740-91-01
SUPPLEMENTARY TEST PROCEDURE 030
CLASS 7025
Power Distribution Unit (PDU)
(Ref. Appendix A-62)
1. General
This procedure provides a description of special test equipment, fixturing, cabling, instrumentation, and instructions for
performing the inspection and evaluations applicable to Power Distribution Unit (PDU).
2. Test Equipment/Test Setup
All tests are to be performed under the following environmental conditions, unless otherwise stated:
23 + 10C (73+ 18F)
Temperature:
Relative Humidity:
80 percent maximum
All test equipment is to be energized for at least 30 minutes prior to utilization, unless otherwise specified in operating
manual for the test equipment.
All tests are to be performed in a electromagnetic shielded enclosure, if in a high RF field of interference.
Table B-1 list the test equipment, and Figure B-1, B-2, B-3, B-4 and B-5 illustrates the various test setups.
Table B-1.. Test Equipment for Procedure
Item
Technical Manual (Ref.)
Digital Voltmeter, Hewlett-Packard, Model 3439A
NA
Multimeter, AN/PSM-6
NA
Power Supply, Hewlett-Packard, Model 6269B (PS1)
NA
Power Supply, Hewlett-Packard, Model 6255A (2 required; PS1/PS2)
NA
Megohmeter, James Biddle
NA
High Current Jumper (Commercial)
NA
Resistor, 130 ohm, 10%, 3W, (Commercial) (2 Required) NA
Battery, BB-590/U
NA
3. Inspection Requirements.
The following mechanical-visual inspections are applicable to all Power Distribution Units series system, sets, units, and
assemblies and further define the coded inspection criteria given in appendix A.
(a)
Visual Inspection
(1)
All decals are in place and all nomenclature is legible.
(2)
All external connectors are securely mounted, free from
damage and missing pins, have protective covers installed.
Change 1 B-130.27
|